From a 3 GW intercontinental electricity bridge to a 4 GW desert transmission corridor, Saudi Arabia is building a new generation of power highways. This guide examines the major HVDC developments, their technology, converter stations, transmission packages, publicly reported contractors and status. Research cut-off: 26 November 2026.
Saudi Arabia’s major HVDC projects at a glance
| Project | DC voltage / capacity | Route | Evidence-based status |
|---|---|---|---|
| Saudi–Egypt | ±500 kV / 3 GW | Madinah–Tabuk–Badr | 1.5 GW phase 1 energized; full operation not independently confirmed |
| Yanbu–NIC South | ±525 kV / 3 GW | Western Saudi Arabia, ~605 km OHTL scheme | Awarded; published target 2027 |
| NEOM additional links | Up to 6 GW combined | Two further links | Early works and capacity reservation announced |
| Riyadh PP14–Kudmi | 500 kV class / 4 GW | 1,089 km | OHTL contracts awarded |
| Al-Fadhili GCCIA | 1.8 GW upgrade rating | Back-to-back, no long DC line | Existing since 2009; upgrade announced |
| EOA–COA Link 1 | 500 kV class / 3 GW | Nariyah–Zulff, ~508 km | Award reported April 2026 |
| EOA–COA Link 2 | 500 kV class; MW not verified | Qurayyah-4/Hajer-2–Khari, ~466 km | Tender reported; award not verified |
The known headline capacities total up to 20.8 GW when the full 9 GW NEOM program is included, excluding Link 2. This is an arithmetic sum of announced link ratings, not installed capacity, new generation or simultaneous transfer capability. The 3 GW Yanbu project is included in the 9 GW program and must not be counted twice.
1. Saudi Arabia–Egypt electricity interconnection
This cross-border link joins the Saudi 60 Hz and Egyptian 50 Hz grids without requiring synchronous AC operation. The 2021 contract announcement established a 3 GW, ±500 kV multi-terminal LCC (line-commutated converter) system. It combines overhead lines with a submarine crossing in the Gulf of Aqaba. Published route lengths differ: Hitachi Energy describes about 1,000 km, while the IEA gives 1,350 km for the wider route. These figures should not be treated as identical measurement boundaries.
| Converter terminal | AC interface | Installed converter rating |
|---|---|---|
| Madinah | 380 kV | 2 × 1,500 MW |
| Tabuk | 380 kV | 2 × 750 MW |
| Badr, Egypt | 500 kV | 2 × 1,500 MW |
Terminal ratings are not additive transfer capacity. The 3 GW network limit and dispatch constraints govern exchanges. Hitachi Energy supplies the core converter technology; Orascom Construction publicly identifies its consortium scope at Badr and Taba. Hyundai E&C identifies its Madinah–Tabuk–Aqaba line work. Other Saudi package allocations in the original draft require independent confirmation before publication.
Status: Saudi Energy’s FY2025 results presentation confirms energization of the 1.5 GW first phase. August 2026 reporting describes ongoing technical trials toward full operation; commercial operation at the full 3 GW rating has not been independently established in this review.
Sources: Hitachi Energy project data | IEA | Saudi Energy FY2025 results | August 2026 trials report | Orascom annual report
2. Yanbu–NEOM Industrial City (NIC South): 3 GW VSC link
The initial NEOM transmission link uses voltage-source converter (VSC) technology at ±525 kV. Both terminals connect to 380 kV AC networks; two 1,500 MW converter units form the 3 GW bipole. Hitachi Energy provides converter engineering, technology and commissioning, while SSEM undertakes AC equipment and construction/installation responsibilities under the consortium arrangement. SEC acts as EPCM partner to ENOWA.
| Package | Publicly identified contractor | Details |
|---|---|---|
| Converter stations | Hitachi Energy / SSEM | YCNT and NIC South; SSEM lists SAR 1.49 billion for its project entry |
| OHTL Portion I | Hyundai E&C | 207 km, about 450 towers; USD 145 million; July 2027 target |
| OHTL Portion II | Not independently verified | Original draft allocation not published as confirmed |
| OHTL Portion III | Larsen & Toubro | 200 km; SDEC engineering reference PTS-22WM309 |
Hyundai describes the OHTL scheme as 605 km, whereas the technology supplier describes a wider connection exceeding 650 km. Route definitions differ or may reflect design revisions; no reconciliation is assumed. Hitachi lists 2027 as the commissioning target, not a guarantee.
Sources: ENOWA | Hitachi Energy | SSEM project reference | Hyundai award | SDEC Portion III
3. NEOM’s two additional HVDC links
The 2023 agreements also cover early works and manufacturing capacity reservation for two further systems, each up to 3 GW. Together with Yanbu–NIC, the announced program could reach 9 GW. This is a development plan, not proof that all three projects have full EPC awards or are under construction. Their final routes, schedules and contract values were not verified. CESI also describes owner-engineer services for the Yanbu/NIC South 3 GW scheme; its use of the term Phase II should not be counted as another independent 3 GW link.
Sources: 2023 agreement | CESI
4. Riyadh PP14–Kudmi: a 4 GW domestic power corridor
The project links the Riyadh PP14 generation area with Kudmi in southwestern Saudi Arabia. Hyundai’s November 2024 announcement identifies a 1,089 km, 500 kV-class double-bipolar HVDC line with 4 GW transfer capacity. Such a corridor can strengthen regional power transfers and improve flexibility between geographically separated generation and demand centers.
| OHTL contractor | Publicly reported scope/value |
|---|---|
| Hyundai E&C | 369 km; USD 725 million; January 2027 section target |
| Larsen & Toubro | SAR 1.51 billion contract, reported November 2024 |
| SSEM | Third section identified by trade reporting; length/value not verified |
The OHTL package targets are not dates for full system commercial operation. Converter OEM, terminal configuration details and converter station awards were not independently verified here.
Sources: Hyundai official announcement | L&T and SSEM trade report
5. Al-Fadhili: the GCC’s asynchronous HVDC bridge
Al-Fadhili is fundamentally different from the long-distance systems. Its rectifier and inverter are located together in a back-to-back station, allowing the Saudi 60 Hz system to exchange power with the GCC 50 Hz network. The facility entered service in 2009. GCCIA and Hitachi Energy announced a control and protection modernization contract in March 2023, with an announced post-upgrade exchange rating of 1,800 MW. The OEM lists 2026 for commissioning of the upgrade; completion was not independently verified.
Source: Hitachi Energy/GCCIA announcement
6. Eastern–Central Operating Area Link 1: Nariyah–Zulff
MEED reported on 20 April 2026 that Alfanar Projects had been selected for a roughly USD 500 million OHTL contract. The proposed 508 km, 500 kV-class HVDC line is rated at 3 GW, connecting Nariyah with Zulff BSP. The report attributes the award to a project source; no direct owner announcement was identified here. Converter suppliers, station awards and commissioning dates remain unverified.
7. Eastern–Central Operating Area Link 2: Qurayyah–Khari
The same MEED report identifies a planned second corridor of approximately 466 km from the Qurayyah-4/Hajer-2 area to Khari Industrial City substation. Bids had reportedly been submitted. No final contractor or MW rating was independently confirmed, and the project is treated as a pipeline item rather than an awarded or operational asset.
Source for both eastern-central developments: MEED, 20 April 2026
8. How HVDC actually works
An AC switchyard feeds converter transformers and power electronic valves. The sending terminal converts AC to DC; overhead conductors or cables transfer energy; the receiving terminal converts it back to AC. Power direction and magnitude are controlled electronically.
Power calculation: for a balanced bipole, P ≈ 2 × Vpole × Idc. A ±525 kV, 3 GW link carries approximately 2,857 A per pole at rated power, ignoring losses. A ±500 kV, 3 GW bipole carries approximately 3,000 A. The pole-to-pole voltage is 1,050 kV and 1,000 kV respectively, not the pole-to-earth voltage.
| Feature | LCC HVDC | VSC HVDC |
|---|---|---|
| Valve technology | Thyristors | Self-commutated semiconductor valves, often MMC |
| Grid dependency | Normally needs strong AC voltage for commutation | Can support weaker grids with suitable controls |
| Reactive power | Typically substantial filter/compensation needs | Independent P/Q control within capability limits |
| Power reversal | Typically voltage polarity reversal in conventional scheme | Typically DC current reversal |
| Saudi example | Saudi–Egypt | Yanbu–NIC |
The technology selection depends on grid strength, transmission medium, required control functions, losses, footprint and economics. Black-start capability is design dependent, not automatic for every VSC system.
9. Major equipment and EPC work breakdown
| Package | Typical engineering and procurement scope |
|---|---|
| AC switchyard | GIS/AIS, breakers, CTs/VTs, arresters, busbars |
| Converter transformers | Insulation, harmonic duty, cooling, transport and installation |
| Valve halls | Thyristor or MMC valves, cooling, valve control and shielding |
| DC yard | Reactors, measuring devices, disconnectors, arresters, DC filters where needed |
| Transmission lines | Survey, geotechnical investigation, tower design, foundations, conductors, insulators, OPGW |
| Auxiliary systems | AC/DC supplies, UPS, HVAC, fire protection, water cooling |
| Control and protection | Pole/bipole control, protection, SCADA, telecom, cyber security |
| Testing | Factory tests, subsystem integration, energization and grid performance tests |
An HVDC tender should distinguish technology-OEM scope from local EPC scope, OHTL and cable packages, AC grid reinforcement and owner interfaces. Key study deliverables include AC/DC load flow, EMT, insulation coordination, harmonic and resonance assessment, transient overvoltage, grounding and reliability studies.
10. Why Saudi Arabia is investing in HVDC
Long transmission distances, renewable resource geography, interregional exchange and asynchronous international connections make HVDC useful. DC overhead lines avoid AC charging-current and steady-state reactive-power constraints, while DC cables are particularly attractive for long submarine distances. Converter costs and losses mean HVDC is not automatically cheaper or more efficient at every distance. Project-specific economics matter.
11. Related engineering guides
Inside a 380 kV BSP • Substation tendering and contract management • Transmission line efficiency • Grid-forming BESS vs synchronous condensers • Transient recovery voltage
Frequently asked questions
What is the largest announced Saudi domestic HVDC corridor in this guide? Riyadh–Kudmi is rated 4 GW; NEOM’s 9 GW figure describes three links rather than one link.
Can Saudi Arabia and Egypt exchange electricity despite different frequencies? Yes. HVDC decouples the AC frequencies.
Is a 380 kV double-circuit OHTL an HVDC line? Not necessarily. D/C frequently means double circuit in AC project descriptions and should not be confused with direct current.
Are all listed projects operational? No. They include existing assets, awarded projects and planned developments. Always distinguish energization, testing and commercial operation.
Conclusion
Saudi Arabia’s HVDC portfolio spans international exchange, renewable-ready VSC transmission, regional bulk power corridors and asynchronous grid coupling. For engineering professionals, these projects create opportunities in converter technology, AC substations, overhead lines, protection, civil construction and commissioning. This article is based on public sources; unverified package allocations, dates and technical ratings have intentionally been excluded or marked uncertain. The featured illustration is conceptual and does not depict a specific project.