Auxiliary Transformer Sizing (Substation Primary Design Course)

Posted on December 25, 2025December 25, 2025 by Engr. Hamid Ali

In this post, we wil explain auxiliary transformer sizing, as per SEC/National Grid standards. Auxiliary transformers play a critical but often underestimated role in substation design. While power transformers transmit energy to the grid, auxiliary transformers ensure the substation itself stays alive—supplying power to protection, control, HVAC, lighting, motors, communication systems, and essential services.This is our 5th post that is part of Extra High Voltage EHV Substation Design & 380kV Substation Design. If you are new on our website it is recommended to read first the below Posts

  • 380kV Gantries & Gantry Equipment
  • Inside a 380kV BSP: Overall Layout Drawing Explained
  • 380kV Gas-Insulated Switchgear (GIS)
  • Power Transformers

1. Why Auxiliary Transformer Sizing Matters

Most project technical specifications mention a minimum auxiliary transformer rating, but accepting these values without verification represents a significant engineering risk. During the design stage, detailed calculations must substantiate or challenge these preliminary figures. This verification process isn’t merely bureaucratic—it’s fundamental to ensuring decades of reliable substation operation.

  • That value is often generic
  • It may not reflect actual connected loads
  • It may ignore future expansion
  • It may violate loading limits defined by standards

👉 Design engineers are responsible for verification, not blind acceptance.

Improper sizing can lead to:

  • Overloading and premature failure
  • Nuisance tripping
  • Inability to support future bays or equipment
  • Safety and reliability risks
SST

2. Key Factors for SST Sizing

To size an auxiliary transformer, engineers must consider:

2.1 Ultimate Substation Configuration:

Account for current and future load requirements (e.g., planned expansions).Transformer sizing must account for both current requirements and future load growth. Substations often expand over their 30-40 year operational lifespan, and auxiliary systems must accommodate this evolution without requiring premature transformer replacement.

Design Philosophy: Size for the 20-year horizon, not just today’s needs. This forward-looking approach represents the most cost-effective lifecycle strategy

2.2 80% Loading Limit:

As per the SEC standard TES-P-119.35, clause 3.1.2 it is required that simultaneous peak loading on the auxiliary transformer excluding the power transformer oil filtration socket load shall not exceed 80% of the station service transformer capacity. This 20% margin serves multiple purposes:

  • Improves efficiency by operating in the optimal region of the load curve
  • Accommodates unexpected load spikes
  • Reduces thermal stress, extending transformer life
  • Provides capacity for unanticipated future loads

2.3 Diversity Factor:

A multiplier to reflect realistic load demand (e.g., not all loads operate at full capacity simultaneously). Diversity factors recognize that not all connected loads operate simultaneously at their maximum capacity. To understand diversity factor we must understand continuous and momentary loads,

Continuous vs. Momentary Loads

Continuous Loads:

  • HVAC systems (when maintaining 25°C room temperature)
  • 125V DC battery chargers
  • Protection and control panels
  • Communication equipment
  • Cubic lighting

Momentary/Intermittent Loads:

  • Sump pump motors
  • Transformer WTTC (Wait Tap Changer) motors
  • Circuit breaker operating motors
  • Oil filtration systems (specifically excluded from continuous calculations per TSP 119.35 Clause 3.1.4)

Diversity Factor Application Guidelines

  1. Lighting Loads: Diversity factor = 1.0 (all considered fully loaded)
  2. Receptacles: 50% loading assumption for indoor/outdoor receptacles
  3. Panel Heaters: Excluded if full HVAC load included (maintains 25°C)
  4. Duct Heaters: Excluded when HVAC load fully accounted
  5. Receptacle Groups: One receptacle per group assumed continuously loaded

2.4 Standards Compliance:

Adherence to

  • Project Specification PTS-XXXXXXX- Project Technical Specification
  • SEC Standard: TES-P-119.35.Rev-0 – Station Auxiliary Transformer Sizing
  • SEC Standard: TES-P-119.30.Rev-2 – Auxiliary AC/DC Panels

Step-by-Step Sizing Methodology

Phase 1: Data Collection and Documentation

  1. Comprehensive Load Inventory: Obtain complete AC load listing from project client, including all future planned loads
  2. Standards Review: Thoroughly study applicable standards for load categorization requirements
  3. Equipment Specifications: Gather detailed specifications for all substation equipment with AC loads

Phase 2: Tabular Load Analysis

The systematic approach utilizes a detailed table structure (as exemplified in Table 1 for a 13.8kV/400-230V auxiliary transformer):

EquipmentRated KVAQuantityTotal Rated KVADiversity FactorOperating KVA
125V Battery Charger5021000.550
Lighting Panels60.129160.1291.060.129
HVAC System751751.075
………………

Phase 3: Calculation and Selection

Example Calculation:

  1. Sum Operating KVA: Total all operating KVA values from table
    • Example: 358 KVA (sum of diversified loads)
  2. Apply 80% Loading Rule:Required Rating=Total Operating KVA0.8=3580.8=448 KVARequired Rating=0.8Total Operating KVA​=0.8358​=448 KVA
  3. Select Standard Rating: Choose next available market standard size
    • 448 KVA → Select 500 KVA transformer

It is strongly recommended that you have the Idea about Number of AC & DC Panels required inside a BSP. Panels Required in Substations

Typical Loads of a 380/132kV BSP MAIN DB BUS-1

Feeder No.DescriptionVoltageLoad in kW (a)Quantity (b)Connected Load (c) = (a)x(b)Diversity Factor (d)Operated Load (e) = (c)x(d)
1.1300A, OIL FILTERATION SOCKET (SGT-1)400147.221147.220.000.0
1.2300A, OIL FILTERATION SOCKET (SGT-2)400147.221147.220.000.0
1.3300A, OIL FILTERATION SOCKET (SGT-3)400147.221147.220.000.0
1.4300A, OIL FILTERATION SOCKET (BUS REACTOR)400147.221147.220.000.0
1.5300A, OIL FILTERATION SOCKET (LINE REACTOR)400147.221147.220.000.0
1.6300A, OIL FILTERATION SOCKET (LINE REACTOR)400147.221147.220.000.0
1.7300A, OIL FILTERATION SOCKET (LINE REACTOR-FUTURE)400147.221147.220.000.0
1.8300A, OIL FILTERATION SOCKET (LINE REACTOR-FUTURE)400147.221147.220.000.0
1.9300A, OIL FILTERATION SOCKET (T-301)400147.221147.220.000.0
1.10SDB-1 (CONTROL BUILDING) SUPPLY-140029.31129.310.5014.7
1.11SDB-2 (380kV GIS BUILDING) SUPPLY-140088.03188.030.5044.0
1.12SDB-3 (132kV GIS-1 BUILDING) SUPPLY-14003.2313.230.501.6
1.13SDB-4 (132kV GIS-2 BUILDING) SUPPLY-14003.2313.230.501.6
1.14SDB-5 COMMUNICATION DB (COMMUNICATION ROOM) SUPPLY-14005.0015.000.502.5
1.15SDB-6 (CUSTOMER ROOM) SUPPLY-140022.78122.780.5011.4
1.16SDB-7 COMMUNICATION DB (CUSTOMER ROOM) SUPPLY-14004.0014.000.502.0
1.17SDB-8 (PUMP ROOM) SUPPLY-14005.8615.860.502.9
1.18SDB-9 (SECURITY BUILDING) SUPPLY-140053.60153.600.5026.8
1.19ILP-1 (CONTROL BUILDING) SUPPLY-140022.96122.960.5011.5
1.20ILP-2 (380kV GIS BUILDING) SUPPLY-140016.95116.950.508.5
1.21ILP-3 (132kV GIS-1 BUILDING) SUPPLY-140011.41111.410.505.7
1.22ILP-4 (132kV GIS-2 BUILDING) SUPPLY-140011.41111.410.505.7
1.23ILP-5 (CUSTOMER ROOM) SUPPLY-14003.3713.370.501.7
1.24OLP-1 (CONTROL BUILDING) SUPPLY-140040.14140.140.5020.1
1.25OLP-2 (380kV GIS BUILDING) SUPPLY-140050.88150.880.5025.4
1.26HVAC POWER PANEL-1 (380kV GIS BUILDING) SUPPLY-140087.10187.100.5043.6
1.27HVAC POWER PANEL-2 (380kV GIS BUILDING) SUPPLY-140087.10187.100.5043.6
1.28HVAC POWER PANEL-3 (380kV GIS BUILDING) SUPPLY-140087.10187.100.5043.6
1.29HVAC POWER PANEL-4 (132kV GIS-1 BUILDING) SUPPLY-140070.40170.400.5035.2
1.30HVAC POWER PANEL-5 (132kV GIS-1 BUILDING) SUPPLY-140070.40170.400.5035.2
1.31HVAC POWER PANEL-6 (132kV GIS-2 BUILDING) SUPPLY-140070.40170.400.5035.2
1.32HVAC POWER PANEL-7 (132kV GIS-2 BUILDING) SUPPLY-140070.40170.400.5035.2
1.33HVAC POWER PANEL-8 (CONTROL BUILDING) SUPPLY-140070.40170.400.5035.2
1.34HVAC POWER PANEL-9 (CONTROL BUILDING) SUPPLY-1400150.001150.000.5075.0
1.35HVAC POWER PANEL-10 (CUSTOMER ROOM) SUPPLY-140030.00130.000.5015.0
1.36HVAC CONTROL PANEL-1 (380kV GIS BUILDING) SUPPLY-140015.00115.000.050.8
1.37HVAC CONTROL PANEL-2 (380kV GIS BUILDING) SUPPLY-140015.00115.000.050.8
1.38HVAC CONTROL PANEL-3 (380kV GIS BUILDING) SUPPLY-140015.00115.000.050.8
1.39HVAC CONTROL PANEL-4 (132kV GIS-1 BUILDING) SUPPLY-140015.00115.000.050.8
1.40HVAC CONTROL PANEL-5 (132kV GIS-1 BUILDING) SUPPLY-140015.00115.000.050.8
1.41HVAC CONTROL PANEL-6 (132kV GIS-2 BUILDING) SUPPLY-140015.00115.000.050.8
1.42HVAC CONTROL PANEL-7 (132kV GIS-2 BUILDING) SUPPLY-140015.00115.000.050.8
1.43HVAC CONTROL PANEL-8 (CONTROL BUILDING) SUPPLY-140015.00115.000.050.8
1.44HVAC CONTROL PANEL-9 (CONTROL BUILDING) SUPPLY-140015.00115.000.050.8
1.45HVAC CONTROL PANEL-10 (CUSTOMER ROOM) SUPPLY-140010.00110.000.050.5
1.46125V DC BATTERY CHARGER-1 (380kV GIS SYSTEM)400106.251106.250.5053.1
1.47125V DC BATTERY CHARGER-3 (132kV GIS SYSTEM)40087.50187.500.5043.8
1.4848V DC BATTERY CHARGER-1 (COMMUNICATION ROOM)40033.60133.600.5016.8
1.49COOLING FAN SUPPLY – SGT-1 SUPPLY-140046.35146.350.5023.2
1.50COOLING FAN SUPPLY – SGT-2 SUPPLY-140046.35146.350.5023.2
1.51COOLING FAN SUPPLY – SGT-3 SUPPLY-140046.35146.350.5023.2
1.52COOLING FAN SUPPLY – SGT-4 SUPPLY-140046.35146.350.5023.2
1.53COOLING FAN SUPPLY – SGT-5 SUPPLY-140046.35146.350.5023.2
1.54COOLING FAN SUPPLY – SGT-6 SUPPLY-140046.35146.350.5023.2
1.5563A, GAS FILLING RECEPTACLE (380kV GIS)40030.92130.920.000.0
1.5663A, GAS FILLING RECEPTACLE (380kV GIS)40030.92130.920.000.0
1.5763A, GAS FILLING RECEPTACLE (380kV GIS)40030.92130.920.000.0
1.5863A, GAS FILLING RECEPTACLE (380kV GIS) (FUT.)40030.92130.920.000.0
1.5963A, GAS FILLING RECEPTACLE (132kV GIS-1)40030.92130.920.000.0
1.6063A, GAS FILLING RECEPTACLE (132kV GIS-1)40030.92130.920.000.0
1.6163A, GAS FILLING RECEPTACLE (132kV GIS-1)40030.92130.920.000.0
1.6263A, GAS FILLING RECEPTACLE (132kV GIS-2)40030.92130.920.000.0
1.6363A, GAS FILLING RECEPTACLE (132kV GIS-2)40030.92130.920.000.0
1.6463A, GAS FILLING RECEPTACLE (132kV GIS-2)40030.92130.920.000.0
1.6563A, GAS FILLING RECEPTACLES FOR OUTDOOR GIB40030.92130.920.000.0
1.6663A, GAS FILLING RECEPTACLES FOR OUTDOOR GIB40030.92130.920.000.0
1.6763A, GAS FILLING RECEPTACLES FOR OUTDOOR GIB40030.92130.920.000.0
1.6863A, GAS FILLING RECEPTACLES FOR OUTDOOR GIB40030.92130.920.000.0
1.6963A, GAS FILLING RECEPTACLES FOR OUTDOOR GIB40030.92130.920.000.0
1.7063A, GAS FILLING RECEPTACLES FOR OUTDOOR GIB40030.92130.920.000.0
1.7163A, RECEPTACLE FOR GAS FILLING/WELDING AT 380kV GANTRY AREA40030.92130.920.000.0
1.7263A, RECEPTACLE FOR GAS FILLING/WELDING AT 380kV GANTRY AREA40030.92130.920.000.0
1.7363A, RECEPTACLE FOR GAS FILLING/WELDING AT 132kV GANTRY AREA40030.92130.920.000.0
1.7463A, RECEPTACLE FOR GAS FILLING/WELDING AT 132kV GANTRY AREA40030.92130.920.000.0
1.7563A, WELDING RECEPTACLE FOR POWER TRANSFORMER SGT-140030.92130.920.000.0
1.7663A, WELDING RECEPTACLE FOR POWER TRANSFORMER SGT-240030.92130.920.000.0
1.7763A, WELDING RECEPTACLE FOR POWER TRANSFORMER SGT-340030.92130.920.000.0
1.7863A, WELDING RECEPTACLE FOR REACTORS40030.92130.920.000.0
1.7963A, WELDING RECEPTACLE FOR SST-140030.92130.920.000.0
1.8063A, WELDING RECEPTACLE FOR PACU 1A (380kV GIS BUILDING)40030.92130.920.000.0
1.8163A, WELDING RECEPTACLE FOR PACU 2A (380kV GIS BUILDING)40030.92130.920.000.0
1.8263A, WELDING RECEPTACLE FOR PACU 3A (380kV GIS BUILDING)40030.92130.920.000.0
1.8363A, WELDING RECEPTACLE FOR PACU 4A (132kV GIS-1 BUILDING)40030.92130.920.000.0
1.8463A, WELDING RECEPTACLE FOR PACU 5A (132kV GIS-1 BUILDING)40030.92130.920.000.0
1.8563A, WELDING RECEPTACLE FOR PACU 6A (132kV GIS-2 BUILDING)40030.92130.920.000.0
1.8663A, WELDING RECEPTACLE FOR PACU 7A (132kV GIS-2 BUILDING)40030.92130.920.000.0
1.8763A, WELDING RECEPTACLE FOR PACU 8A (CONTROL BUILDING)40030.92130.920.000.0
1.8863A, WELDING RECEPTACLE FOR PACU 9A (CONTROL BUILDING)40030.92130.920.000.0
1.8963A, WELDING RECEPTACLE FOR PACU 10A (CUSTOMER ROOM)40030.92130.920.000.0
1.90HV TEST SOCKET (380kV GIS BUILDING)40030.92130.920.000.0
1.91HV TEST SOCKET (132kV GIS-1 BUILDING)40030.92130.920.000.0
1.92PORTABLE CHARGER-1 (125V DC BATTERY CHARGER-1)40029.42129.420.000.0
1.93PORTABLE CHARGER-3 (125V DC BATTERY CHARGER-3)40029.42129.420.000.0
1.94SDB-10 (EXTERNAL TELECOM SHELTER) SUPPLY-14008.0018.000.504.0
1.95VENTILATION CONTROL PANEL (380kV GIS BUILDING) SUPPLY-140025.00125.000.051.3
1.96VENTILATION CONTROL PANEL (132kV GIS-1 BUILDING) SUPPLY-140050.00150.000.052.5
1.97VENTILATION CONTROL PANEL (132kV GIS-2 BUILDING) SUPPLY-140050.00150.000.052.5
1.98VENTILATION CONTROL PANEL (CONTROL BUILDING) SUPPLY-140050.00150.000.052.5

Typical Loads of a 380/132kV BSP MAIN DB BUS-2

Feeder No.DescriptionVoltageLoad in kW (a)Quantity (b)Connected Load (c) = (a)x(b)Diversity Factor (d)Operated Load (e) = (c)x(d)
2.1300A, OIL FILTERATION SOCKET (SGT-4)400147.221147.220.000.0
2.2300A, OIL FILTERATION SOCKET (SGT-5)400147.221147.220.000.0
2.3300A, OIL FILTERATION SOCKET (SGT-6)400147.221147.220.000.0
2.4300A, OIL FILTERATION SOCKET (BUS REACTOR)400147.221147.220.000.0
2.5300A, OIL FILTERATION SOCKET (LINE REACTOR)400147.221147.220.000.0
2.6300A, OIL FILTERATION SOCKET (LINE REACTOR)400147.221147.220.000.0
2.7300A, OIL FILTERATION SOCKET (LINE REACTOR-FUTURE)400147.221147.220.000.0
2.8300A, OIL FILTERATION SOCKET (LINE REACTOR-FUTURE)400147.221147.220.000.0
2.9300A, OIL FILTERATION SOCKET (T-302)400147.221147.220.000.0
2.10SDB-1 (CONTROL BUILDING) SUPPLY-240029.31129.310.5014.7
2.11SDB-2 (380kV GIS BUILDING) SUPPLY-240088.03188.030.5044.0
2.12SDB-3 (132kV GIS-1 BUILDING) SUPPLY-24003.2313.230.501.6
2.13SDB-4 (132kV GIS-2 BUILDING) SUPPLY-24003.2313.230.501.6
2.14SDB-5 COMMUNICATION DB (COMMUNICATION ROOM) SUPPLY-24005.0015.000.502.5
2.15SDB-6 (CUSTOMER ROOM) SUPPLY-240022.78122.780.5011.4
2.16SDB-7 COMMUNICATION DB (CUSTOMER ROOM) SUPPLY-24004.0014.000.502.0
2.17SDB-8 (PUMP ROOM) SUPPLY-24005.8615.860.502.9
2.18SDB-9 (SECURITY BUILDING) SUPPLY-240053.60153.600.5026.8
2.19ILP-1 (CONTROL BUILDING) SUPPLY-240022.96122.960.5011.5
2.20ILP-2 (380kV GIS BUILDING) SUPPLY-240016.95116.950.508.5
2.21ILP-3 (132kV GIS-1 BUILDING) SUPPLY-240011.41111.410.505.7
2.22ILP-4 (132kV GIS-2 BUILDING) SUPPLY-240011.41111.410.505.7
2.23ILP-5 (CUSTOMER ROOM) SUPPLY-24003.3713.370.501.7
2.24OLP-1 (CONTROL BUILDING) SUPPLY-240040.14140.140.5020.1
2.25OLP-2 (CONTROL BUILDING) SUPPLY-240050.88150.880.5025.4
2.26HVAC POWER PANEL-1 (380kV GIS BUILDING) SUPPLY-240087.10187.100.5043.6
2.27HVAC POWER PANEL-2 (380kV GIS BUILDING) SUPPLY-240087.10187.100.5043.6
2.28HVAC POWER PANEL-3 (380kV GIS BUILDING) SUPPLY-240087.10187.100.5043.6
2.29HVAC POWER PANEL-4 (132kV GIS-1 BUILDING) SUPPLY-240070.40170.400.5035.2
2.30HVAC POWER PANEL-5 (132kV GIS-1 BUILDING) SUPPLY-240070.40170.400.5035.2
2.31HVAC POWER PANEL-6 (132kV GIS-2 BUILDING) SUPPLY-240070.40170.400.5035.2
2.32HVAC POWER PANEL-7 (132kV GIS-2 BUILDING) SUPPLY-240070.40170.400.5035.2
2.33HVAC POWER PANEL-8 (CONTROL BUILDING) SUPPLY-240070.40170.400.5035.2
2.34HVAC POWER PANEL-9 (CONTROL BUILDING) SUPPLY-2400150.001150.000.5075.0
2.35HVAC POWER PANEL-10 (CUSTOMER ROOM) SUPPLY-240030.00130.000.5015.0
2.36HVAC CONTROL PANEL-1 (380kV GIS BUILDING) SUPPLY-240015.00115.000.050.8
2.37HVAC CONTROL PANEL-2 (380kV GIS BUILDING) SUPPLY-240015.00115.000.050.8
2.38HVAC CONTROL PANEL-3 (380kV GIS BUILDING) SUPPLY-240015.00115.000.050.8
2.39HVAC CONTROL PANEL-4 (132kV GIS-1 BUILDING) SUPPLY-240015.00115.000.050.8
2.40HVAC CONTROL PANEL-5 (132kV GIS-1 BUILDING) SUPPLY-240015.00115.000.050.8
2.41HVAC CONTROL PANEL-6 (132kV GIS-2 BUILDING) SUPPLY-240015.00115.000.050.8
2.42HVAC CONTROL PANEL-7 (132kV GIS-2 BUILDING) SUPPLY-240015.00115.000.050.8
2.43HVAC CONTROL PANEL-8 (CONTROL BUILDING) SUPPLY-240015.00115.000.050.8
2.44HVAC CONTROL PANEL-9 (CONTROL BUILDING) SUPPLY-240015.00115.000.050.8
2.45HVAC CONTROL PANEL-10 (CUSTOMER ROOM) SUPPLY-240010.00110.000.050.5
2.46125V DC BATTERY CHARGER-2 (380kV GIS SYSTEM)400106.251106.250.5053.1
2.47125V DC BATTERY CHARGER-4 (132kV GIS SYSTEM)40087.50187.500.5043.8
2.4848V DC BATTERY CHARGER-2 (COMMUNICATION ROOM)40033.60133.600.5016.8
2.49COOLING FAN SUPPLY – SGT-1 SUPPLY-240046.35146.350.5023.2
2.50COOLING FAN SUPPLY – SGT-2 SUPPLY-240046.35146.350.5023.2
2.51COOLING FAN SUPPLY – SGT-3 SUPPLY-240046.35146.350.5023.2
2.52COOLING FAN SUPPLY – SGT-4 SUPPLY-240046.35146.350.5023.2
2.53COOLING FAN SUPPLY – SGT-5 SUPPLY-240046.35146.350.5023.2
2.54COOLING FAN SUPPLY – SGT-6 SUPPLY-240046.35146.350.5023.2
2.5563A, GAS FILLING RECEPTACLE (380kV GIS)40030.92130.920.000.0
2.5663A, GAS FILLING RECEPTACLE (380kV GIS)40030.92130.920.000.0
2.5763A, GAS FILLING RECEPTACLE (380kV GIS)40030.92130.920.000.0
2.5863A, GAS FILLING RECEPTACLE (380kV GIS) (FUT.)40030.92130.920.000.0
2.5963A, GAS FILLING RECEPTACLE (132kV GIS-1)40030.92130.920.000.0
2.6063A, GAS FILLING RECEPTACLE (132kV GIS-1)40030.92130.920.000.0
2.6163A, GAS FILLING RECEPTACLE (132kV GIS-1)40030.92130.920.000.0
2.6263A, GAS FILLING RECEPTACLE (132kV GIS-2)40030.92130.920.000.0
2.6363A, GAS FILLING RECEPTACLE (132kV GIS-2)40030.92130.920.000.0
2.6463A, GAS FILLING RECEPTACLE (132kV GIS-2)40030.92130.920.000.0
2.6563A, GAS FILLING RECEPTACLES FOR OUTDOOR GIB40030.92130.920.000.0
2.6663A, GAS FILLING RECEPTACLES FOR OUTDOOR GIB40030.92130.920.000.0
2.6763A, GAS FILLING RECEPTACLES FOR OUTDOOR GIB40030.92130.920.000.0
2.6863A, GAS FILLING RECEPTACLES FOR OUTDOOR GIB40030.92130.920.000.0
2.6963A, GAS FILLING RECEPTACLES FOR OUTDOOR GIB40030.92130.920.000.0
2.7063A, GAS FILLING RECEPTACLES FOR OUTDOOR GIB40030.92130.920.000.0
2.7163A, RECEPTACLE FOR GAS FILLING/WELDING AT 380kV GANTRY AREA40030.92130.920.000.0
2.7263A, RECEPTACLE FOR GAS FILLING/WELDING AT 380kV GANTRY AREA40030.92130.920.000.0
2.7363A, RECEPTACLE FOR GAS FILLING/WELDING AT 132kV GANTRY AREA40030.92130.920.000.0
2.7463A, RECEPTACLE FOR GAS FILLING/WELDING AT 132kV GANTRY AREA40030.92130.920.000.0
2.7563A, WELDING RECEPTACLE FOR POWER TRANSFORMER SGT-440030.92130.920.000.0
2.7663A, WELDING RECEPTACLE FOR POWER TRANSFORMER SGT-540030.92130.920.000.0
2.7763A, WELDING RECEPTACLE FOR POWER TRANSFORMER SGT-640030.92130.920.000.0
2.7863A, WELDING RECEPTACLE FOR REACTORS40030.92130.920.000.0
2.7963A, WELDING RECEPTACLE FOR SST-240030.92130.920.000.0
2.8063A, WELDING RECEPTACLE FOR PACU 1B (380kV GIS BUILDING)40030.92130.920.000.0
2.8163A, WELDING RECEPTACLE FOR PACU 2B (380kV GIS BUILDING)40030.92130.920.000.0
2.8263A, WELDING RECEPTACLE FOR PACU 3B (380kV GIS BUILDING)40030.92130.920.000.0
2.8363A, WELDING RECEPTACLE FOR PACU 4B (132kV GIS-1 BUILDING)40030.92130.920.000.0
2.8463A, WELDING RECEPTACLE FOR PACU 5B (132kV GIS-1 BUILDING)40030.92130.920.000.0
2.8563A, WELDING RECEPTACLE FOR PACU 6B (132kV GIS-2 BUILDING)40030.92130.920.000.0
2.8663A, WELDING RECEPTACLE FOR PACU 7B (132kV GIS-2 BUILDING)40030.92130.920.000.0
2.8763A, WELDING RECEPTACLE FOR PACU 8B (CONTROL BUILDING)40030.92130.920.000.0
2.8863A, WELDING RECEPTACLE FOR PACU 9B (CONTROL BUILDING)40030.92130.920.000.0
2.8963A, WELDING RECEPTACLE FOR PACU 10B (CUSTOMER ROOM)40030.92130.920.000.0
2.90HV TEST SOCKET (380kV GIS BUILDING)40030.92130.920.000.0
2.91HV TEST SOCKET (132kV GIS-2 BUILDING)40030.92130.920.000.0
2.92PORTABLE CHARGER-2 (125V DC BATTERY CHARGER-2)40029.42129.420.000.0
2.93PORTABLE CHARGER-4 (125V DC BATTERY CHARGER-4)40029.42129.420.000.0
2.94SDB-10 (EXTERNAL TELECOM SHELTER) SUPPLY-24008.0018.000.504.0
2.95VENTILATION CONTROL PANEL (380kV GIS BUILDING) SUPPLY-240025.00125.000.051.3
2.96VENTILATION CONTROL PANEL (132kV GIS-1 BUILDING) SUPPLY-240050.00150.000.052.5
2.97VENTILATION CONTROL PANEL (132kV GIS-2 BUILDING) SUPPLY-240050.00150.000.052.5
2.98VENTILATION CONTROL PANEL (CONTROL BUILDING) SUPPLY-240050.00150.000.052.5

Load Summary

DescriptionValue
Total load at MDB1698.1 kW
Total load at MDB in kVA1997.8 kVA
The simultaneous peak load on Auxiliary Transformer excluding Oil Filtration Socket (80% of the AUX.TXFR. rating)1997.8 kVA
Load of Oil Filtration Socket in kVA147.22 / 0.85 = 173.20 kVA
The simultaneous peak load on Auxiliary Transformer including Oil Filteration Socket(1997.81 + 173.2) = 2171.0 kVA
Hence Selected Auxiliary Transformer rating2500.0 kVA

«Previous Post

Our Top Posts

  • List of Contractors who Won Major BSP Projects in 2024 in KSA
  • Top Electrical Engineering Courses on Coursera
  • List of Top Substation contractors in KSA
  • Transmission Line Design Important Points
  • Panels required inside substations
  • Electrical MCQs with Explanation of Answers
  • Electrical Past papers
  • How to Add MCQs in wordpress posts
  • Transmission Lines design Basics
  • 380kV Substation Design (17)
  • Al BABTAIN (1)
  • Al Gihaz (3)
  • AL-OJAIMI (1)
  • Alsharif Group (1)
  • Basic Electrical (7)
  • Basic Electronics (5)
  • BSP Projects (17)
  • Communication System (1)
  • Control System (2)
  • Control System MCQs (3)
  • Courses (5)
  • electrical (8)
  • Electrical Courses (5)
  • Electrical Jobs (7)
  • Electrical MCQs (12)
  • Electronics MCQs (9)
  • Extra High Voltage EHV Substation Design (18)
  • Fellowships (2)
  • Fellowships in Pakistan (1)
  • FPSC (1)
  • HVDC Projects (1)
  • Information for Engineers (37)
  • Interview Preparation (28)
  • Jobs (10)
  • Jobs in KSA (11)
  • MATLAB and Simulink (1)
  • MCQs (13)
  • Microsoft Excel (2)
  • Microwaves MCQs (1)
  • NTS Past Papers (4)
  • OHTL Projects (7)
  • Past Papers (10)
  • Research Work (4)
  • Safety MCQs (2)
  • Saudi ARAMCO (3)
  • Scholarships (3)
  • Scholarships in Pakistan (1)
  • Scholarships in Pakistan (1)
  • SEC Projects (20)
  • SSEM (2)
  • Synchronous Condensers (2)
  • TDP (1)
  • Transmission lines design (7)
  • Uncategorized (24)
  • Web Development (1)

Latest Posts

  • Auxiliary Transformer Sizing (Substation Primary Design Course)
  • The Rise of SF6-Free Switchgear: Alternatives, Advantages, and the Road Ahead
  • Safety Assessment at Saudi Aramco Part 3
  • Classification of Lightning Protection Systems
  • Safety Assessment at Saudi Aramco Part 2

All Pages

  • Active Scholarships
  • C++ Data Structures
  • Electrical MCQs with explanation
  • Jobs
  • Privacy Policy
  • Technical Posts
  • The World of Engineers
  • Top Electrical MCQs with explanation

Follow Us on

  • Facebook
  • YouTube
  • LinkedIn

© 2025 The World of Engineers | Powered by Superbs Personal Blog theme